Copy one of these electrical prompts, change the bracketed parts, and paste it into your AI.
Service calls and new leads
Add a lead in Projul for a new client, [Dana Whitaker], phone [(435) 555-0188]. Call it [Whitaker 200A Service Upgrade], job at [742 N Bluff St]. She has a 100 amp fuse panel and wants 200 amp service with an EV charger circuit. Likelihood [70]%.
Schedule an estimate meeting on [Whitaker 200A Service Upgrade] in Projul for [Thursday 9 to 10 am] with [Marcus Hale], and note that the panel is on the north wall behind the gate.
Follow-ups and the pipeline
Log on [Whitaker 200A Service Upgrade] in Projul that I called [Dana] this morning, reached her, and she is waiting on the utility to confirm the meter location.
Which leads in Projul have had no follow-up logged in the last [10] days? Give me the client, the stage and the last conversation.
Estimates
Build an estimate in Projul for [Whitaker 200A Service Upgrade] with four sections: [permits and utility coordination], [service and panel], [circuit transfer and labeling], [EV charger circuit]. [Give the quantities, your costs and your markups for each line.]
On the [Whitaker 200A Service Upgrade] estimate in Projul, raise the journeyman labor to [20] hours and change the SER cable to [28] lf.
Options, visibility and tax
On the [Whitaker 200A Service Upgrade] estimate in Projul, make the [EV charger circuit] section a selection where the client must choose one: [NEMA 14-50 receptacle at $1,120] or [hardwired 48A charger at $1,865]. Start with the receptacle selected.
Apply our [Utah] sales tax to the [Perez Kitchen Remodel] estimate in Projul.
Change orders
Add a change order to [Perez Kitchen Remodel] in Projul called [Knob-and-tube removal in kitchen ceiling]: [180 lf of 12/2 NM-B at $1.35] plus [25]%, [boxes and devices, 1 lot at $95] plus [25]%, and [14] hours at [$58] plus [40]%.
Scheduling and crews
Create a task on [Ridgeline Lot 14 Rough Wiring] in Projul called [Rough-in] for [Tuesday through Thursday, 7 am to 3:30 pm]. Put [Marcus Hale] and [Tyler Boone] on Tuesday and Wednesday, and [Marcus Hale] alone on Thursday.
The [200A panel] is backordered to [September 22]. Move [Service change, power off] on [Whitaker 200A Service Upgrade] in Projul to [September 24] and log on the job why.
Inspections and deadlines
Add these steps to the [Service change, power off] task on [Whitaker 200A Service Upgrade] in Projul: [confirm utility disconnect on site, photograph existing panel and directory, set meter main and drive ground rods, land feeders and torque terminations, transfer and label all circuits, photograph the new directory, call for inspection].
Photos and job records
Upload [whitaker-panel-before.jpg] and [whitaker-panel-after.jpg] to [Whitaker 200A Service Upgrade] in Projul and label them [Existing fuse panel] and [New 200A load center, directory labeled].
End-of-week questions
What is on the schedule in Projul next week, by person and by job?
Check the [Ridgeline Lot 14 Rough Wiring] estimate in Projul for anything odd: lines with no cost, sections with no lines, missing tax, or a margin under [20]%.
Note: Anything that creates or changes a record needs a Read-Write key; questions work with either key. Publishing, invoicing, the time clock and purchase orders are done in Projul, not by your AI.

Watch it work
Short videos of Projul AI Connect doing this kind of job:
- Site visit notes to estimate (1:06)
- Voicemail to new lead (0:47)
- Shift the schedule for a delay (0:49)